§ 18.60.160. ESTABLISHMENT OF USE OR STRUCTURE.  


Latest version.
  • Establishment of a use or approved structure shall occur within two (2) years of the effective date of permit approval, unless a different time period is established as part of the approval. The establishment term may be lengthened to match the establishment term of a concurrent land use application on the subject property. The use or structure shall be considered established when the provisions of either subsection .010 or subsection .020 below are met:
    .010 All the following exist:
    .0101 All required conditions of approval have been satisfied;
    .0102 All required construction permits have been obtained and completed,
    .0103 All grading work, structural foundations, and final inspections have been completed; and
    .0104 A certificate of occupancy has been issued and bonds guaranteeing site improvements have been released; or
    .020 All required conditions of approval have been satisfied for a use not requiring any building permits, and the use is operating in compliance with such approval. (Ord. 5920 § 1 (part); June 8, 2004: Ord. 6245 § 86; June 5, 2012.)